The contractor has completed the structural concrete work and concrete barrier construction. The remaining work includes bringing in fill material for the green spaces, top soil, grass pavers, guardrails, and flat work such as concrete entrances, curb and gutter, and sidewalk paver replacement.
Dominion Energy is scheduled to energize the new traffic cabinet at the end of December. This will allow the contractor to complete the replacement of the traffic signals and pedestrian signals at the Route 1 and 20th Street intersection.